This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

PESSOAS-FSE+-01431000

Purpose of the operation

Anexo 2_MEMÓRIA DESCRITIVA_CLDS 5G (Ponto 2. Justificação/Objetivos/Descrição da Operação_Pag.6)

How the operation is framed

Programme
Programa Demografia, Qualificações e Inclusão
Fund
Fundo Social Europeu Mais
Policy objective
+ Social
Specific objective
Igualdade no acesso a serviços de qualidade e em tempo útil.
Thematic area
Dinâmicas territoriais
Economic activity
Administração Local
Modality
Subvenção
Co-financing rate
85%

Published territorial distribution

ChavesAlto Tâmega · Norte
100% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
1 January 2025
Actual start
17 March 2025
Planned completion
31 December 2028
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.

View the official Portugal 2030 portal ↗Captures validated by SHA-256; source checked on 18 November 2026.