Mar · Em Execução

(MAR-111.2.1-FEAMPA-00082) Modernização da embarcação JOÃO DIANA PRT000022485 PTEPS-114656-L

JOSE ANTONIO DA SILVA NEVES

Fund approved
€9,694.30
Fund executed
€7,335.30
Fund paid
€7,335.30

This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

MAR2030-FEAMPA-01295900

Purpose of the operation

Modernizar a embarcação com equipamentos eletrónicos atuais

How the operation is framed

Programme
Programa MAR2030
Fund
Fundo Europeu dos Assuntos Marítimos, das Pescas e da Aquicultura
Policy objective
+ Verde
Specific objective
Reforçar as atividades de pesca sustentáveis do ponto de vista económico, social e ambiental.
Thematic area
Mar
Economic activity
Pesca marítima
Modality
Subvenção
Co-financing rate
70%

Published territorial distribution

EsposendeCávado · Norte
100% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
1 August 2024
Actual start
30 October 2024
Planned completion
30 June 2025
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.

View the official Portugal 2030 portal ↗Captures validated by SHA-256; source checked on 18 November 2026.