Mar · Em Execução

(mar-111.2.1-feampa-00047) modernização da embarcação rumo à lua

PEREIRA DA ROSA & GONÇALVES PEREIRA, LDA

Fund approved
€104,723.33
Fund executed
€51,355.50
Fund paid
€51,355.51

This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

MAR2030-FEAMPA-00578800

Purpose of the operation

INVESTTIMENTOS PARA MELHORIA DAS CONDIÇÕES DE SEGURANÇA, HABITABILIDADE, TRABALHO E EFICIENCIA ENERGÉTICA

How the operation is framed

Programme
Programa MAR2030
Fund
Fundo Europeu dos Assuntos Marítimos, das Pescas e da Aquicultura
Policy objective
+ Verde
Specific objective
Reforçar as atividades de pesca sustentáveis do ponto de vista económico, social e ambiental.
Thematic area
Mar
Economic activity
Pesca marítima
Modality
Subvenção
Co-financing rate
52.5%

Published territorial distribution

Vila do CondeÁrea Metropolitana do Porto · Norte
100% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
1 February 2024
Actual start
6 October 2024
Planned completion
31 December 2024
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.

View the official Portugal 2030 portal ↗Captures validated by SHA-256; source checked on 18 November 2026.