Energia · Em Execução

GREENMETAL – Descarbonização e Eficiência Energética na Metalomecânica

APEMETA-ASSOCIAÇÃO PORTUGUESA DE EMPRESAS DE TECNOLOGIAS AMBIENTAIS

Fund approved
€630,015.87
Fund executed
€0.00
Fund paid
€44,968.86

This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

COMPETE2030-FEDER-03128100

Purpose of the operation

-

How the operation is framed

Programme
Programa Inovação e Transição Digital
Fund
Fundo Europeu de Desenvolvimento Regional
Policy objective
+ Verde
Specific objective
Promover a eficiência energética e reduzir as emissões de gases com efeito de estufa.
Thematic area
Energia
Economic activity
Fabricação de portas, janelas e elementos similares em metal
Modality
Subvenção
Co-financing rate
85%

Published territorial distribution

-- · Centro
50% of the location
-- · Norte
50% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
16 February 2026
Actual start
16 February 2026
Planned completion
15 February 2028
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.

View the official Portugal 2030 portal ↗Captures validated by SHA-256; source checked on 18 November 2026.