Investigação, Desenvolvimento e Inovação · Em Execução

Membranas ativas de fibras de madeira para a captura e transformação de microplásticos

REQUIMTE - REDE DE QUIMICA E DE TECNOLOGIA - ASSOCIAÇÃO

Fund approved
€211,800.96
Fund executed
€8,583.32
Fund paid
€28,046.75

This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

COMPETE2030-FEDER-00798300

Purpose of the operation

The main objective of the present operation is to develop new membrane separation and reaction units based on functional wood fibers, with high microplastics capturing capacity from water and high (photo)catalytic activity for microplastics transformation into value-added materials. To achieve the main objective, a series of specific objectives were outlined: 1) Utilization of wood fibers from pine wood scraps, as a cheap and abundant Portuguese resource, for the preparation of innovative eco-friendly membranes. 2) Wood fibers functionalization with active units using biocompatible reactants, recyclable solvents, and microwave heating. 3) Use of computer modeling to obtain insightful information on the physisorption process of plastic polymers on different wood fibers surface compositions.…

Read the full published description

The main objective of the present operation is to develop new membrane separation and reaction units based on functional wood fibers, with high microplastics capturing capacity from water and high (photo)catalytic activity for microplastics transformation into value-added materials. To achieve the main objective, a series of specific objectives were outlined: 1) Utilization of wood fibers from pine wood scraps, as a cheap and abundant Portuguese resource, for the preparation of innovative eco-friendly membranes. 2) Wood fibers functionalization with active units using biocompatible reactants, recyclable solvents, and microwave heating. 3) Use of computer modeling to obtain insightful information on the physisorption process of plastic polymers on different wood fibers surface compositions. 4) Develop membrane separation units based on a natural polymer and deep eutectic solvents, aiming an optimized, sustainable, technical, and economically viable separation process. 5) Conducting experimental tests to evaluate the effectiveness of wood fibers membranes for microplastics removal from wastewater and aquifers from the north region of Portugal. 6) Carry out an evaluation of the effect of surface water salinity on the efficiency of the process. 7) Develop a Proof-of-Concept for a separation unit to be tested in a wastewater treatment plant effluent. 8) Explore the catalytic and photo-assisted depolymerization of plastics such as polyesters, polyamides, polycarbonates, polyurethanes, using NaBH4 as a reducing agent, widely considered as a low-cost H2 storage material. 9) Explore the fragmentation of alkane-backbone based polymers such as polyethylene, polypropylene, polystyrene, by catalytic/photocatalytic oxidation with a green oxidant such as hydrogen peroxide. 10) Recover aromatic monomers obtained from plastics catalytic depolymerization for the purpose of creating advanced fluorescent materials for integration into devices and sensors.

How the operation is framed

Programme
Programa Inovação e Transição Digital
Fund
Fundo Europeu de Desenvolvimento Regional
Policy objective
+ Inteligente
Specific objective
Reforçar a investigação, inovação e adoção de tecnologias avançadas.
Thematic area
Investigação, Desenvolvimento e Inovação
Economic activity
Outra investigação e desenvolvimento das ciências físicas e naturais
Modality
Subvenção
Co-financing rate
85%

Published territorial distribution

PortoÁrea Metropolitana do Porto · Norte
63.9216% of the location
AveiroRegião de Aveiro · Centro
36.0784% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
1 June 2025
Actual start
6 November 2025
Planned completion
30 May 2028
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.

View the official Portugal 2030 portal ↗Captures validated by SHA-256; source checked on 18 November 2026.