This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

NORTE2030-FEDER-02536400

Purpose of the operation

Dotar os operacionais com 76 EPI adequado, conferindo desta forma proteção integral nas ocorrências no âmbito dos Incêndios Florestais.

How the operation is framed

Programme
Programa Regional do Norte
Fund
Fundo Europeu de Desenvolvimento Regional
Policy objective
+ Verde
Specific objective
Adaptação às alterações climáticas, prevenindo riscos e aumentando a resiliência a catástrofes.
Thematic area
Alterações Climáticas
Economic activity
Fabricação de equipamento de proteção e segurança
Modality
Subvenção
Co-financing rate
83.18%

Published territorial distribution

Vale de CambraÁrea Metropolitana do Porto · Norte
100% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
2 September 2025
Actual start
2 September 2025
Planned completion
19 February 2026
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.

View the official Portugal 2030 portal ↗Captures validated by SHA-256; source checked on 18 November 2026.