Mar · Em Execução

(MAR-111.2.1-FEAMPA-00262) Bruno Miguel do Couto Leal, LESLIE, PRT000016645

BRUNO MIGUEL DO COUTO LEAL

Fund approved
€4,540.12
Fund executed
€4,540.12
Fund paid
€4,540.12

This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

MAR2030-FEAMPA-02307200

Purpose of the operation

GARMIN,FORCE KRAKEN 90 MOTO ARRASTO ELÉTRICO 100lb White,GARMIN,TOMADA ELÉT. MACHO P/M.KRAKEN,GARMIN,TOMADA ELÉT. FEMEA P/M.FORCE KRAKEN,GARMIN,DISJUNTOR 42V 60A W.,GARMIN,QUILHA P/M.FORCE KRAKEN,GARMIN,PLACA DE LIB.,KIT ESTAB.,PACK BATERIA

How the operation is framed

Programme
Programa MAR2030
Fund
Fundo Europeu dos Assuntos Marítimos, das Pescas e da Aquicultura
Policy objective
+ Verde
Specific objective
Reforçar as atividades de pesca sustentáveis do ponto de vista económico, social e ambiental.
Thematic area
Mar
Economic activity
Culturas de produtos hortícolas, raízes e tubérculos
Modality
Subvenção
Co-financing rate
70%

Published territorial distribution

VelasRegião Autónoma dos Açores · Região Autónoma dos Açores
100% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
19 December 2024
Actual start
15 October 2025
Planned completion
31 October 2025
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.

View the official Portugal 2030 portal ↗Captures validated by SHA-256; source checked on 18 November 2026.