Investigação, Desenvolvimento e Inovação · Em Execução

Desenvolvimento de Medicamentos Inovadores para Acne – Abrindo Novos Caminhos

UNIVERSIDADE DA BEIRA INTERIOR

Fund approved
€100,750.49
Fund executed
€0.00
Fund paid
€8,110.44

This page sets out the fields Portugal 2030 publishes about the operation: approved funding, administrative execution, framing and territory. The merit of the application and results on the ground are not in this source.

CENTRO2030-FEDER-02362100

Purpose of the operation

The general aim of the present project is to set the basis for the development of novel topical medicines against acne vulgaris. One first specific aim is to achieve an optimized formulation based on the described innovative SNEDDS or NE of Capryol® 90 as lead formulation, which could be considered suitable for cutaneous administration in the treatment of acne and potentially safe for use by pre-adolescents and pregnant women, according to the following criteria: rational selection of its components, considering literature information on their effect on human skin; physicochemical and organoleptic attributes; efficacy in at least one of the in vitro models of acne vulgaris hallmarks (keratinocyte proliferation, C. acnes overgrowth and/or dysbiotic shift, anti-inflammatory effect, sebocyte…

Read the full published description

The general aim of the present project is to set the basis for the development of novel topical medicines against acne vulgaris. One first specific aim is to achieve an optimized formulation based on the described innovative SNEDDS or NE of Capryol® 90 as lead formulation, which could be considered suitable for cutaneous administration in the treatment of acne and potentially safe for use by pre-adolescents and pregnant women, according to the following criteria: rational selection of its components, considering literature information on their effect on human skin; physicochemical and organoleptic attributes; efficacy in at least one of the in vitro models of acne vulgaris hallmarks (keratinocyte proliferation, C. acnes overgrowth and/or dysbiotic shift, anti-inflammatory effect, sebocyte proliferation and/or sebum production) and concomitant efficacy against strains associated with Malassezia folliculitis; safety (in in vitro reconstituted skin models) and acceptability... suitable packaging and stability. With exception of stability studies, this is expected to be achieved during the first 6 months. A second specific aim is to test whether any of the previously developed 5a-Reductase inhibitors have potential as a candidate anti-acne drug. To provide evidence of such, we intend to characterize the compounds’ effect on androgen receptor (AR), their selectivity against 5a-Reductase subtypes and ability to inhibit sebum production. Simultaneously, we intend to study their pre-formulation properties, to select the best suitable candidate for the development of a new drug product. This is expected to be achieved during the first 9 months of the project, and overlaps in time the previous objective. A third specific aim is to develop follow-up combination formulations by incorporating a retinoid (trifarotene) and the most promising 5a-Reductase inhibitor to obtain a medicine potentially effective in all acne hallmarks. These new formulations will be tested to meet the criteria already defined for the previous formulations. This aim will be pursued approximately during the second half of the project timeline.

How the operation is framed

Programme
Programa Regional do Centro
Fund
Fundo Europeu de Desenvolvimento Regional
Policy objective
+ Inteligente
Specific objective
Reforçar a investigação, inovação e adoção de tecnologias avançadas.
Thematic area
Investigação, Desenvolvimento e Inovação
Economic activity
Atividades de investigação
Modality
Subvenção
Co-financing rate
83.98%

Published territorial distribution

CovilhãBeiras e Serra da Estrela · Centro
100% of the location

Location as shown in the file of 31 October 2026.

Published schedule

Planned start
1 February 2026
Actual start
4 May 2026
Planned completion
31 July 2027
Actual completion
Not given

Official source and release dates

Operation and amounts: 31 October 2026. Location: 31 October 2026.